Quarterly power supply revenue ₹4,019cr, EBITDA ₹3,835cr
High EBITDA from operational contracted plants; below-EBITDA financing matters
Watch: Check cash flow and debt conversion
Home / Research / Adani Green Energy Limited
Quarterly power supply revenue ₹4,019cr, EBITDA ₹3,835cr
High EBITDA from operational contracted plants; below-EBITDA financing matters
Watch: Check cash flow and debt conversion
Operational expansion and margins appear positive
Watch: Check like-for-like generation and curtailment
Issuer-defined operating earnings, not consolidated free cash flow
Watch: Review financing bridge
Margin expansion in the half year
Watch: Track tariff and utilization
*Quarter ended 30 September 2026 · Issuer-source research brief prepared 18 November 2026 · Based on accepted Adani Green earnings transcript [S1] and investor presentation [S2]. Not an independently certified statutory reconciliation, valuation opinion or target price.*
The first visual exhibits show reported Q2 power-supply revenue, power-supply EBITDA and growth, followed by H1 financial scale, renewable electricity sold, operational capacity and storage commissioned. Later exhibits distinguish operational plants from forward targets, and project-finance leverage from operating margin. The company produces contracted renewable power and is building the ability to shift electricity to periods of stronger demand through battery and pumped-hydro storage. A high power-supply EBITDA margin is not a high free-cash-flow margin: financing costs, construction capital and cash collections remain economically material. [S1][S2]
Key takeaways
But the ratio between a business-specific EBITDA measure and power-supply sales must not be casually redefined as statutory consolidated EBITDA divided by statutory consolidated revenue. [S1]
At 30 September 2026 the operational renewable portfolio stood around 20.8 GW, above an important 20-GW threshold. During H1, energy sales reached 25.7 billion units, up 32% year on year, with company-disclosed operational growth coming from renewable additions.
These figures show scale expanding through physically generating plants rather than announcements alone. They do not establish that every planned plant is connected to an unconstrained evacuation network.
Transmission congestion at Khavda remains a decisive operational issue. [S1][S2]
The value-creation variant is the extension from solar/wind megawatts to dispatchable clean energy. Management said 3 GWh of batteries were commissioned at Khavda during Q2, taking installed battery storage to 6.6 GWh, and described a plan to exceed 10 GWh during FY27.
That makes storage a meaningful operating asset rather than simply a slide-deck aspiration. The economic question is the incremental revenue, curtailment avoided, storage cycling and financing cost versus the installed capital per usable MWh.
The commissioning milestone is encouraging; project-level return data remains essential. [S1]
A large, continuing ₹2.4 lakh crore capex programme through FY30 and management discussion of around 5.6x leverage create an asymmetric investor task: EBITDA and contracted cash flow may grow, but delays in grid evacuation or commissioning can leave debt funding ahead of contracted generation. Management anticipates a gradual leverage reduction later in the decade as operating assets replace construction assets.
That is a future financing trajectory, not a current deleveraging event. [S1]
What valuation would demand: a dated share count, enterprise-value bridge, gross debt and cash, project-specific power-purchase tariffs, sustainable operating cash after finance costs, construction cash requirements and the price actually available to investors. Those inputs have not been reconciled for this report and no fabricated multiple, fair value or target appears. Continue monitoring the company as a financing-and-execution business as well as a renewable growth business.
Key takeaways
The exact accounting definition is the company's disclosed power-supply measure. [S1]
For H1 FY27, power-supply revenue was ₹8,299 crore, up 36%, and power-supply EBITDA ₹7,957 crore, up 41%. The presentation separately lists cash profit of ₹4,176 crore, up 35%, while management referred to total H1 EBITDA of ₹8,276 crore.
This is not four interchangeable measures. A cash-profit definition is not necessarily reported cash generated from operating activities; a power-supply operating EBITDA excludes some business or reconciliation lines that may appear in group total EBITDA.
Investors should ask for a full bridge rather than silently adding or substituting them. [S1][S2]
A major counterfactual concerns curtailment. Management said that total H1 EBITDA of ₹8,276 crore could have approached approximately ₹9,000 crore in the absence of curtailed output. The approximate ₹724 crore arithmetic difference is a management-suggested scenario, not billed power supply and not a booked receivable.
Actual revenue recovery depends on evacuation, storage dispatch, contractual treatment, time of day and project availability. This potential foregone output is a reason to focus on grid progress, not to inflate earnings used in the valuation denominator.
[S1]
Half-year electricity sales of 25.7 billion units, up 32%, establish that generation/dispatch is growing alongside capacity. The physical unit measure provides a valuable independent cross-check on revenue growth, although tariff mix, weather, solar versus wind resource conditions, new-asset commissioning dates and plant load factors still affect rupee outcomes.
This report does not infer a consolidated average tariff from power-supply revenue divided by all energy units because contract and recognition bases may differ. [S1]
The revenue-to-EBITDA growth spread is positive at both Q2 and H1, but durable cash yield cannot be concluded from it. Commissioned assets with long-term PPAs may offer predictable revenue for many years, while new construction consumes capital before commercial operation.
The right quarterly financial table must show power-supply sales and EBITDA, total EBITDA, PAT, operating cash flow, interest paid, capex cash outflow and net debt on consistent dates. Where complete statutory CFO and debt details are not in the retrieved passages, no absolute financial value is invented.
[S1][S2]
Key takeaways
A 6.6-GWh battery system does not itself represent 6.6 GW of generating capacity; the power rating and discharge duration must be evaluated separately. [S1][S2]
Asset economics begin with generation yield, contractual tariff and collection. A commissioned megawatt produces economic value when resource availability, equipment performance and grid connections allow contracted power to be delivered.
Curtailment can reduce realized revenue despite the plant being built and technically available. This is why the company's Khavda grid evacuation bottleneck matters more than a simple headline capacity target.
Transmission assets are partly executed by third parties and right-of-way problems may delay energization. [S1]
Management cited 3 GWh of battery storage commissioned in Q2, raising operating storage to 6.6 GWh, more than half of India's operating BESS according to its own description. Storage can absorb renewable generation that otherwise would be curtailed and release it later, but the commercial value depends on round-trip losses, availability, cycle life, warranty terms, how dispatch is remunerated and whether any grid bottleneck remains at the actual point of injection.
A large battery fleet without an economic dispatch protocol may reduce energy loss but not necessarily earn an attractive incremental equity return. [S1]
The company also described a 500-MW pumped-storage project at Chitravathi as progressing toward completion near year-end. Pumped hydro is a different asset and risk class from lithium batteries, with long construction timelines, geological/site constraints and separate power-to-energy-duration characteristics. The development pipeline should not be treated as operating output until commissioning and contracted dispatch are demonstrably complete. [S1]
Counterparty and duration risk matter. Management's cited strategy includes securing long-term contracts, seeking AA+ counterparties and targeting project equity returns in a 13–14% range. Those return thresholds are management underwriting aims, not the realized ROE of every newly commissioned asset or a guarantee of PPA performance.
A disciplined public report must compare signed contractual offtake, debtor concentration, actual collection behavior and project financing against these stated standards. [S1]
Key takeaways
That is an important distinction: the engineering readiness of a solar park cannot by itself solve a constrained transmission corridor. [S1]
Management described its previous FY27 capacity commissioning aspiration of 4.5–5 GW as contingent on the timing of the relevant transmission corridor. It explained that an anticipated connection had shifted later, potentially toward the following quarter, and that project balance-of-system preparations were being advanced so final module deployment could respond quickly once evacuation certainty improves.
This should be recorded as a *conditional capacity plan*, not as achieved commissioning or guaranteed FY27 EBITDA. [S1]
The opportunity to improve utilization through batteries is real but should be linked to the exact bottleneck. If solar output is curtailed at midday, a properly connected BESS asset can shift dispatch and capture otherwise wasted generation.
Whether BESS can operate before every grid corridor is ready depends on local interconnection and the offtake contract. The claim that storage 'insulates' the portfolio from transmission delay requires quantification through observed MWh dispatched, BESS uptime, contractual payment and reduced curtailment versus the no-storage baseline.
[S1]
Management outlined a target to exceed 10 GWh of batteries during the financial year, versus 6.6 GWh operating after the quarter's additions. The incremental target is about 3.4 GWh beyond the disclosed operating base, but that subtraction is a planning gap, not commissioned capacity.
Tracking installed capacity is one milestone; project economics must later show the dispatch and value actually generated. Similarly, the company's presentation shows a longer-term renewable portfolio ambition but no prospective MW should be silently included in the 20.8-GW operating figure.
[S1][S2]
The management team emphasized remote monitoring, asset analytics and technology-led operating availability. Digital capabilities can support reliability across widespread sites, but high operational EBITDA margins should not substitute for actual reported plant load factors, grid uptime and field-maintenance costs. Promise-versus-delivery analysis should explicitly compare each new commissioning announcement against energization, billing and cash collection in the following period.
Key takeaways
The order of cash flows therefore matters: permitting, land and transmission, equipment procurement, commissioning, generation, billing, collections and debt amortization. Delaying any point after debt drawdown depresses near-term equity returns even if contracted power ultimately performs. [S1]
During Q&A an analyst cited leverage around 5.6x, and management described the near-to-medium-term leverage profile as remaining in that vicinity through FY28–FY29. It anticipated moving toward 4.5–5x after FY29–FY30 as operating assets become a larger share of the portfolio, and eventually potentially below 4x.
These are management perspectives over a long horizon, not a bank-certified net-debt-to-EBITDA reconciliation or a promise that deleveraging begins on a fixed date. A professional report should avoid turning them into an implied one-year multiple.
[S1]
Management stated approximately 72% of project loans were fixed-rate over medium-term periods, offering partial insulation against interest-rate changes. This is meaningful given 25-year fixed-tariff contracts: interest costs are more immediately sensitive to funding markets than contractual tariffs.
Yet a fixed-rate portion leaves a floating/refinancing portion; future debt raising for a huge investment programme also remains exposed to current market rates. A rising-yield environment would therefore still merit stress testing.
[S1]
The ₹4,176 crore H1 cash profit shown in the presentation is not adequate alone to establish free cash flow after interest and capex. Nor does the reported ₹7,957 crore power-supply EBITDA prove that completed and under-construction assets are equally cash generative.
Investors should follow cash-flow-from-operations, cash interest, construction-related capex, project-level restricted balances, shareholder equity injections, debt service and dividend restrictions. No absolute consolidated net-debt number or accounting CFO is invented from incomplete available passages.
[S1][S2]
The equity-return target of 13–14% demands disciplined project selection. Even if asset-level operating margins look exceptional, return on equity depends on leverage, tenure, upfront connection costs, battery replacement reserves and tariff escalation terms.
New BESS contracts may have economics different from traditional contracted renewable generation. The company needs to demonstrate delivered cash returns by asset type rather than aggregate all MW and MWh under one 'renewable' label.
Key takeaways
Debt ratios may remain elevated in the near term because project construction has not peaked. This is an observation-based assessment, not a forecast with invented numeric probabilities.
Constructive case: the Khavda evacuation corridor becomes operational on the revised schedule, prepared plants commission quickly, new contracts meet management's counterparty criteria, and the installed 6.6-GWh BESS fleet demonstrates economic curtailment recovery. Energy delivered and billed grows sustainably, the EBITDA-to-cash conversion improves and new capex can be financed without unexpected equity dilution.
The company would have stronger evidence for adding dispatchable renewable capacity. No price target is estimated because required share and funding inputs are missing.
Adverse case: third-party grid works continue to slip, projects require extra capital while earning no revenue, contracted storage economics prove weaker than presentations imply, or cash collections lag. Fixed tariffs do not immunize new construction against refinancing costs, higher equipment costs or lower generation. A further rise in leverage alongside persistent curtailment would be a more serious risk than one quarter of disappointing growth. [S1]
Key falsifiers are failure of promised commissioning once grid availability is restored; operational batteries that do not materially improve dispatch; sustained divergence between cash profit and cash available after finance and capex; worsening gross leverage despite maturation of the operating portfolio; and counterparty deterioration. The business could continue adding GW while equity economics disappoint if financing and grid timing remain unfavorable.
What might disconfirm the risks: actual grid energization certificates and MW commissioned, BESS discharge MWh and revenue, disclosed interest and operating cash, commissioning-to-billing time, and project-level equity returns. Each metric is observable, has a dated source and should be tracked without assuming management forecasts are already facts.
Key takeaways
First quarterly trigger: report operational renewable MW/GW using the 20.8-GW base at September 2026, then separate grid-connected, commissioned but constrained, and merely under-construction capacity. Check the claimed 4.5–5-GW FY27 commissioning ambition against physical transmission readiness; a fourth-quarter revision is not automatically a project failure but must be explained with independent dated milestones. [S1]
Second trigger: demand a quarterly bridge from Q2 ₹4,019 crore power-supply revenue and ₹3,835 crore power-supply EBITDA to total EBITDA, PAT and reported operating cash. Compare H1 ₹8,299 crore revenue, ₹7,957 crore power-supply EBITDA, ₹8,276 crore total EBITDA and ₹4,176 crore cash profit on their proper definitions, rather than mixing the values in one denominator. [S1][S2]
Third trigger: verify that the installed 6.6-GWh BESS is actually cycling and earning, not merely ready. Track Q2's 3-GWh newly commissioned storage and the remaining gap to the 10-GWh FY27 aspiration. Demand curtailment before/after statistics that distinguish storage benefits from eventual grid restoration. [S1]
Fourth trigger: compare company-disclosed leverage, currently discussed around 5.6x, against management's multiyear amortization path. Verify the 72% fixed-rate loan description, maturity timing and new financing rates; check capitalized interest, project-level security and debt balances. The long-term target of 13–14% ROE on contracted assets should be treated as an underwriting hurdle, not a reported result. [S1]
Fifth trigger: audit actual capital deployment under the ₹2.4 lakh crore FY30 plan. Compare signed PPAs with assets under construction, required equity, cash interest paid and financeable projects. A faster capacity build deserves a higher conviction rating only when its incremental cash economics improve rather than merely when headline megawatts increase.
Investment conclusion: retain WATCH, becoming more constructive on physical grid and BESS economics with sustained cash conversion and managed leverage. A reduction in reported curtailment alongside a stable funding profile would be stronger evidence than upbeat capacity guidance alone. A continued expansion of construction debt without cash-supported commissioning would weaken the thesis.
[S1] Adani Green Energy Q2 FY27 earnings call dated 22 October 2026, issuer document, original Indian issuer: [S2] Adani Green Energy consolidated H1 FY27 earnings presentation, issuer document, original Indian issuer:
Figures refer to issuer-labeled power-supply and group measures. The approximately ₹9,000 crore EBITDA without curtailment, 10-GWh storage goal, 4.5–5 GW commissioning aspiration, long-term ROE targets and future leverage path are management scenarios, not already recognized results. No invented statutory CFO, stock price or valuation multiples are provided.
Original references are in the published manuscript below.
This is dated research, not a live market quote. Scenarios and historical performance are not guarantees.