Clean Max Enviro Energy Solutions Limited — Q2 FY27 Results Analysis

Q2 FY27 growth in revenue and adjusted EBITDA

Published · Quarter Q2 FY27 · CLEANMAX

PeriodQ2 FY27
COMPANY-SPECIFIC GRAPHICAL SUMMARY

What the reported figures reveal

CHART 1

Q2 FY27 growth in revenue and adjusted EBITDA

Revenue Q2 FY26₹5,306 million
Revenue Q2 FY27₹7,277 million
Adjusted EBITDA Q2 FY26₹3,862 million
Adjusted EBITDA Q2 FY27₹5,531 million

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

CHART 2

Revenue from operations first half

H1 FY26₹9,330 million
H1 FY27₹15,598 million

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

CHART 3

Adjusted, not statutory reported EBITDA

H1 FY26₹6,701 million
H1 FY27₹10,472 million

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

CHART 4

H1 profit growth from low base

H1 FY26₹190 million
H1 FY27₹1,201 million

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

ORIGINAL RESEARCH INSIGHTS

Investment findings and watch points

RESEARCH INSIGHT

Q2 FY27 growth in revenue and adjusted EBITDA

Q2 FY27 growth in revenue and adjusted EBITDA

Watch: Monitor profit-to-cash reconciliation

RESEARCH INSIGHT

Revenue from operations first half

Revenue from operations first half

Watch: Monitor profit-to-cash reconciliation

RESEARCH INSIGHT

Adjusted, not statutory reported EBITDA

Adjusted, not statutory reported EBITDA

Watch: Monitor profit-to-cash reconciliation

RESEARCH INSIGHT

H1 profit growth from low base

H1 profit growth from low base

Watch: Monitor profit-to-cash reconciliation

FULL PUBLISHED RESEARCH

Earnings and management commentary analysis

Clean Max Enviro Energy Solutions Limited (CLEANMAX) | Q2 FY27, quarter ended 30 September 2026 | WATCH

Investment decision. CleanMax combines contracted renewable power sales to commercial and industrial customers with renewable energy services. The latest issuer presentation reports 6,270 MW of contracted renewable power sales capacity at 30 September 2026, including 3,638 MW operational and 2,632 MW contracted but not yet executed. The operational base, rather than the entire development portfolio, is what produces current power-sales revenue. The investment thesis depends on commissioning the contracted pipeline, earning adequate cash returns on capital-intensive projects and managing leverage while expanding. [S1]

Q2 FY27 revenue from operations was ₹7,277 million, up 37% from ₹5,306 million in Q2 FY26. Adjusted EBITDA was ₹5,531 million, up 43% from ₹3,862 million; PAT was ₹649 million against ₹356 million. H1 FY27 revenue was ₹15,598 million versus ₹9,330 million; adjusted EBITDA was ₹10,472 million versus ₹6,701 million; PAT was ₹1,201 million versus ₹190 million. Adjusted EBITDA is not identical to reported EBITDA and should not be used interchangeably in valuations. [S1]

Six decision facts

  • Q2 revenue grew 37% year on year to ₹7,277 million, but quarterly revenue was below half-year revenue because of business mix and project timing. [S1]
  • Q2 adjusted EBITDA grew 43% to ₹5,531 million, with an adjustment bridge in the issuer's detailed results. [S1]
  • H1 PAT rose to ₹1,201 million from ₹190 million, a low-base comparison requiring review of interest, tax and accounting items. [S1]
  • Operational renewable power sales capacity rose from 3,088 MW at FY26-end to 3,638 MW at September 2026, a 550 MW increase in the presentation's detailed table. [S1]
  • Contracted but unexecuted renewable power sales capacity stood at 2,632 MW, which is not commissioned capacity. [S1]
  • Management reported a weighted-average debt cost of 8.3% and discussed a CRISIL AA/Stable credit rating; neither is a substitute for consolidated debt and cash-flow reconciliation. [S2]

Valuation discipline. No contemporaneous market price or verified enterprise value is included in these accepted issuer sources. The report therefore does not assign a target price, a share-price upside or an implied market multiple. A premium valuation would require commissioning against signed PPAs, healthy realised tariff and generation, cash returns on capital and sustainable financing costs. A discount would be justified if construction or grid access delays prevent contracted megawatts from producing cash earnings.

Chapter 1 — Business model and decision threshold

CleanMax's renewable power sales business signs long-duration customer agreements and develops power-generating assets. Its services business has different margin characteristics, and the two should not be blended without explanation. A contracted PPA is a valuable demand indicator, but it is not yet an operating asset.

The investor must separately track operational, contracted under execution, evacuation received, and evacuation applied capacity. Management presented the combined portfolio at 13,199 MW in September 2026 versus 7,762 MW roughly 18 months earlier; the 13,199 MW is an aggregate pipeline/portfolio measure, not current revenue-generating megawatts. [S1][S2]

The company has a clear growth pathway but substantial execution requirements. A signed customer agreement may still depend on land, engineering, grid evacuation and commercial commissioning. Management's confidence in future capacity growth should be tested against commissioning certificates and the difference between installed capacity and cash-producing generation. The operating portfolio and financing terms are more meaningful near-term measures than headline portfolio size.

Decision filters

  • Measure commissioned megawatts rather than total pipeline alone.
  • Compare debt cost and actual cash interest with project EBITDA as assets ramp up.
  • Distinguish adjusted EBITDA from reported EBITDA before applying any valuation multiple.
  • Do not treat management's future-year EBITDA guidance as realised profit. [S1][S2]

Chapter 2 — Reported Q2 and H1 financial performance

Consolidated issuer presentation, ₹ million. The table reproduces the issuer's headline reported revenue and PAT alongside its explicitly adjusted EBITDA measure. A statutory EBITDA number should be reconciled separately using the presentation's reported-to-adjusted bridge. [S1]

Financial measureQ2 FY27Q2 FY26H1 FY27H1 FY26
Revenue from operations7,2775,30615,5989,330
Adjusted EBITDA5,5313,86210,4726,701
Profit after tax6493561,201190

The first-half revenue increase of approximately 67% outpaced the 56% growth in adjusted EBITDA. That does not necessarily mean the core power-sales portfolio deteriorated: services mix and corporate/unallocated costs can affect aggregate growth. Q2 adjusted EBITDA increased by approximately 43% while revenue increased 37%, a different quarterly pattern. Investors should evaluate the segment bridge and accounting adjustment bridge rather than infer a single uniform operating margin trend. [S1]

The presentation discloses Q2 power-sales revenue of approximately ₹6,040 million against ₹3,610 million a year earlier, and services revenue of approximately ₹1,637 million versus ₹1,236 million. The segment totals are not necessarily identical to consolidated revenue because unallocated and consolidation adjustments exist; the H1 presentation explicitly notes ₹38 million of unallocated services revenue and negative unallocated EBITDA. Consequently, summing two segment bars without reconciliation would be misleading. [S1]

The issuer's Q2 adjusted EBITDA segment bars include power sales ₹5,257 million and services ₹486 million, against ₹3,377 million and ₹274 million respectively in Q2 FY26, with unallocated services EBITDA negative ₹54 million in Q2 FY27. The figures illustrate the economic dominance of contracted power sales, but they are not the same as consolidated reported EBITDA. [S1]

Earnings-quality questions

  • How much of PAT growth reflects operating assets versus financing and tax movements?
  • What is the precise bridge between reported and adjusted EBITDA?
  • Does higher power-sales adjusted EBITDA convert into cash after interest and maintenance spending?
  • Are newly commissioned projects stabilising on schedule? [S1][S2]

Chapter 3 — Operating capacity, customer and geographic economics

The presentation reports renewable power-sales operational capacity of 1,712 MW at an earlier reference point, 3,088 MW at the beginning of FY27 and 3,638 MW at September 2026. The first-half increase in the detailed table is 550 MW; management's opening remarks rounded commissioned capacity to about 600 MW across the broader discussion. This report uses the detailed 550 MW series for charts and distinguishes the rounded management comment. [S1][S2]

At September 2026, power-sales contracted but unexecuted capacity was 2,632 MW. Renewable energy services separately had 704 MW operational and 127 MW contracted under execution, totalling 831 MW. These services MW should not be added to power-sales operational MW and described as a single owned power-sales fleet. Evacuation capacity received was 3,263 MW, while evacuation applied for was 2,836 MW; neither category is itself an executed PPA or operating power plant. [S1]

The presentation's state table shows operational power-sales capacity at September 2026 including Karnataka 1,104 MW, Gujarat 878 MW, Rajasthan CTU 525 MW, Tamil Nadu 210 MW, Maharashtra 201 MW, Haryana 193 MW and Chhattisgarh 107 MW, plus 420 MW onsite solar spread across multiple jurisdictions. The geography is diversified, but the concentration in Karnataka and Gujarat means regulatory, grid and customer conditions in those states matter disproportionately. [S1]

The contracted portfolio was described as approximately 59% solar and 41% wind. Solar and wind have different generation profiles, capex intensity and project timelines. Management's unit-economics slide cited indicative solar capex of ₹3.5 crore per MWp and wind capex of ₹7.8 crore per MW, excluding soft costs of roughly 5–7% of overall capex. These are issuer-presented unit economics, not verified expenditure for each project. [S1]

Operating tests

  • Compare each quarter's operational MW with the prior quarter's contracted-under-execution MW.
  • Track state-wise commissioning against grid evacuation and PPA start dates.
  • Distinguish solar MWp from wind MW and generation-weighted output.
  • Monitor the services business independently because its margin and revenue recognition differ from owned power sales. [S1]

Chapter 4 — Execution, milestones and management Q&A

Management's November 4 call described a 6.3 GW contracted renewable power-sales portfolio, approximately 3.6 GW operational and 2.6 GW under execution. The detailed presentation quantifies these as 6,270, 3,638 and 2,632 MW. The difference between rounded call commentary and detailed tables is a reporting-precision issue, not an additional pipeline. [S1][S2]

The company presented a minimum 1,500 MW FY27 commissioning objective, with year-end operational capacity of at least 4,588 MW in its illustrative operating assumptions. This is management guidance, not a realised September 2026 figure. Achieving the target would require further commissioning after the 550 MW detailed first-half addition. Grid access, construction and customer onboarding are the practical gates. [S1]

Management also discussed a contracted pipeline that, at a commissioning pace around 1,500 MW annually, represents roughly 20–21 months of growth. That statement assumes a continuing ability to commission and replace the pipeline; it is not a contractual guarantee of revenue recognition within 21 months. The presentation separately shows evacuation received and applied as precursors to future contracting. [S2]

The November call noted that a substantial share of additions came from Gujarat, Karnataka, Maharashtra and Tamil Nadu, industrial markets with significant commercial power demand. This is a strategic concentration in customer-rich states, but it also exposes the pipeline to state-specific open-access regulations and grid constraints. [S2]

Milestone scorecard

  • Verify actual FY27 commissioning against the minimum 1,500 MW management target.
  • Measure the number of MW that move from contracted-under-execution to operational.
  • Review whether evacuation received turns into signed PPAs without disproportionate delay.
  • Compare realised project generation and customer billing with the commissioning certificate date. [S1][S2]

Chapter 5 — Debt, capex, cash conversion and project payback

This is a capital-intensive renewable infrastructure platform. The issuer reported a weighted-average cost of debt of 8.3% in the November call and described a CRISIL AA/Stable rating. These are positive funding indicators, but the economics still depend on debt size, maturity, project cash flows and timing. A lower coupon cannot offset a poor project return indefinitely. [S2]

The issuer's unit-economics slide presented a 5.0–5.5x net-debt-to-run-rate-EBITDA range and a portfolio cash ROIC reference of 13.03% for FY2025, along with a 24-day receivables metric. These are presentation metrics with their own definitions and dates; they should not be silently described as the statutory 30 September 2026 net-debt ratio, current ROIC or current cash conversion. [S1]

The company also presented indicative power-sales tariffs and a weighted-average PPA tenure of approximately 22.85 years. Contract tenure supports visibility, but project cash generation still depends on generation, availability, curtailment, collection, operating costs, financing and maintenance. The long agreement life should not be confused with a guaranteed cash yield. [S1]

Management's FY28 slide described minimum ₹3,000 crore run-rate EBITDA on an illustrative minimum 4.6 GW capacity base, and steady-state net debt around ₹16,000 crore. These are forward-looking issuer assumptions/guidance, not September 2026 reported EBITDA or debt. The report does not include these figures in historical charts or present them as certified forecasts. [S1]

Cash-investment tests

  • Track actual project cash outflow against new MW commissioned, not just announced capex/MW.
  • Monitor interest cost and debt maturities as the asset base expands.
  • Reconcile adjusted EBITDA to statutory operating cash flow and interest paid.
  • Track receivables and actual collection days, especially after new customer onboarding. [S1][S2]

Chapter 6 — Conditional investment scenarios

Bull case — execution converts pipeline to recurring cash earnings. The contracted 2,632 MW under execution progresses to operating status on schedule; new generation contributes to power-sales earnings, funding costs remain manageable and customer collections stay disciplined. The thesis would be strengthened by operational capacity approaching the company's FY27 target and evidence that cash returns on newly commissioned assets support the assumed unit economics. The bull case fails if MW additions do not produce generation and collections. [S1][S2]

Base case — healthy growth but commissioning friction. The existing 3,638 MW operational base supports revenue growth, while some contracted projects experience the usual approval and stabilisation delays. Adjusted EBITDA can grow, but the difference between adjusted profit and cash after interest/capex remains material. In this case a valuation premium should be conditional on stable leverage and real commissioning, not portfolio headline growth alone. [S1]

Bear case — financing and grid bottlenecks. Project commissioning is delayed, the cost of funding rises or evacuation approvals slow; contracted MW remain non-revenue-producing for longer. If the company expands debt before new assets generate cash, leverage and equity value can become sensitive to execution setbacks. This scenario would be weakened by a verified acceleration of commissioned capacity, declining financing cost and strong operating cash conversion. [S1][S2]

These are analytical conditionals, not probability-weighted earnings estimates or stock-price forecasts. The issuer's FY28 run-rate EBITDA guidance remains clearly separate from reported Q2/H1 adjusted EBITDA.

Chapter 7 — Investor action plan and monitoring

Stance: WATCH. The strongest demonstrated advantage is a large operating power-sales fleet plus a signed construction pipeline. The principal investment risk is the timing and cost of converting that pipeline into commissioned, cash-producing assets. Q2/H1 adjusted EBITDA and PAT growth are encouraging but not enough to establish a share-price valuation without the debt/cash bridge and a verified current market price. [S1][S2]

MonitorSeptember 2026 baselineAction test
Operational RE power sales3,638 MWConfirm commissioning and first billings
Power sales under execution2,632 MWTrack transfer into operating MW
Services operational capacity704 MWKeep services distinct from power sales
Evacuation received3,263 MWWatch conversion into contracted projects
Evacuation applied2,836 MWMonitor grid approval milestones
Q2 revenue₹7,277mCompare reported YoY and business mix
Q2 adjusted EBITDA₹5,531mReconcile with reported EBITDA
H1 PAT₹1,201mCompare with cash, tax and financing
Weighted debt cost8.3%, management statementVerify updated borrowing cost
FY27 commissioningMinimum 1,500 MW, guidanceCompare actual full-year MW with target

Catalysts include successful grid commissioning, new customer PPAs, lower funding costs, and strong collections as assets stabilise. Risks include capex overruns, evacuation delays, state open-access rules, tariff or generation shortfalls, refinancing costs and EBITDA adjustments that do not translate into cash.

The report deliberately does not assign a market valuation, current net-debt amount, future dividend or stock-price target. The source material provides strong operating and adjusted financial disclosures, but any investment decision requiring precise enterprise value must use a consistent current valuation date and independently reconciled reported EBITDA, cash and debt.

Original issuer/exchange filings

  • [S1] [BSE-filed CleanMax Q2 FY27 investor presentation, 3 November 2026](https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf)
  • [S2] [BSE-filed CleanMax Q2 FY27 earnings-call transcript, call 4 November and filing 6 November 2026](https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=481a07a7-db11-4b5b-abf3-0c3cad27d442.pdf)

*Financial data is issuer-presented. Adjusted EBITDA is explicitly labelled; issuer guidance, derived comparisons and historical results are not interchangeable.*

Additional company evidence

CHART 5

Q2 PAT

Q2 FY26₹356 million
Q2 FY27₹649 million

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

CHART 6

Commissioned operating power sales

FY26 start1,712 MW
March 20263,088 MW
September 20263,638 MW

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

CHART 7

Operating versus under execution at September 2026

Operational3,638 MW
Under execution2,632 MW

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

CHART 8

Separate renewable services capacity

Operational704 MW
Under execution127 MW

https://www.bseindia.com/stockinfo/AnnPdfOpen.aspx?Pname=d54b57c0-c2b0-4be2-be7e-ce4c2a27517c.pdf

SOURCE REFERENCES

Original disclosures and investor presentations

  1. Issuer disclosure
  2. Issuer disclosure

Related research and comparisons

Other published Q2 FY27 reports

This is dated research, not a live market quote. Scenarios and historical performance are not guarantees.